Vertbois complex at Liège
This building houses a set of offices, stores and apartments over seven levels for a 22 500 m² surface area in all and a 230-spaces car park over three underground levels (3 x 1.900 m²).
The phreatic table level is located three meters beneath the first floor. That’s why a protecting wall was realized by means of 13-meter-deep casted partitions in order to allow the stabilization of the construction into the schist and to watertighten the walls. The pressurizations at the R-3 level are stabilized by a thick slab and a gravel draining layer.
Mission
Complete mission of stability