This Thursday saw the inauguration of KANAL, a museum of modern and contemporary art, architecture and landscape in Brussels.
Built in the early 1930s along the Charleroi-Brussels canal in central Brussels, the Citroën garage was designed by architects Alexis Dumont, Marcel Van Goethem and Maurice-Jacques Ravazé as a cathedral of glass and steel for the automobile. Its many workshops and impressive showroom stood the test of the 20th century, retaining their original function. Through the conversion project that has just been completed, Atelier Kanal, comprising architects noAarchitecten, EM2N and Sergison Bates architects, sought to recapture the original spirit of modernist progress while accommodating the new uses of a cultural and multidisciplinary space open to the city.
As found
In 2015, the Société d’Aménagement Urbain (SAU) of the Brussels-Capital Region purchased the garage to transform it into an international cultural centre.
During the competition launched in 2017, the 7 teams shortlisted from among the 92 entrants discovered a building in its original state, still bearing many traces of its past activities.
The winning team, Atelier Kanal, proposed keeping the complex as found, that is, in the state in which it was discovered. In particular, it retained the volumes, the steel frame, most of the walls and floors, the ramps, the guardrails and the façade frames. Everything remaining of the former Citroën garage that could be retained was preserved, including the names of former spaces (showroom, workshops, changing rooms, carwash). This was an architectural choice rather than a legal requirement, as the building was not subject to heritage listing.
To accommodate the new programme, three new volumes of the same size were built at the heart of the site: the Rassembleur, which houses the offices and auditorium; the archives centre and library of Kanal Architecture; and a new museum of modern and contemporary art.
Today
Since the building was constructed in 1933, standards, regulations, construction techniques, materials, equipment and the urban environment have naturally evolved. What originally complied often no longer does today. Materials have aged. Repairs, adaptations and strengthening are therefore necessary. These are defined on the basis of an extensive campaign of surveys and investigations, which determines which elements are to be retained and which are to be demolished. These investigations, however, remain localised and cannot reveal everything. The discovery of old foundations from the amusement park that occupied the site before the garage was built, groundwater flows and corrosion at the bases of the steel façade columns were among the unexpected findings during construction that required adjustments as the work progressed.
Continuous process
The studies and construction works were part of an evolving, continuous process throughout the project. The engineering studies were carried out up to the preliminary design stage by Buro Happold, the engineering firm that was part of the winning competition team. Bureau greisch then took over until the works were fully completed. This assignment was particularly intensive, involving multiple design assumptions, sophisticated modelling, tests, investigations, unforeseen site conditions, schedule constraints and retrospective checks, all of which continually interacted.
Technical catalogue
The complexity of the existing building and the new structures required an impressive variety of engineering techniques which, taken individually, are nothing exceptional, but which together form an extensive network of structures, ducts, cables and equipment, all dependent on one another. Their integration into the existing structures required studies and highly precise execution.
Bespoke solutions
The variety of existing and new configurations encountered did not allow standardised construction solutions to be used.
In the new buildings, the superimposition of structures with widely differing spans resulted in load paths that were sometimes highly complex. Connecting the structures or separating them to allow for thermal expansion or acoustic isolation required detailed studies.
The existing steel frames were strengthened to support the additional loads associated with the roof’s thermal insulation and the photovoltaic panels. This strengthening involved subtle and very discreet metalwork. The connections are bolted to prevent cracking of the old steel sections.
The complex was divided into three climate zones: the open, light-filled public space, in tune with the seasons, which accounts for half of the floor area; the spaces for exhibiting and conserving artworks, where temperature and humidity are strictly controlled; and the glazed galleries, which serve as intermediate thermal spaces.
The integration of ducts, cables and technical equipment was adjusted as the project developed to make their presence as unobtrusive as possible while ensuring easy access.
Whether integrated or clearly expressed, the structures and technical equipment were designed with simplicity and efficiency in mind, in keeping with the industrial and modernist spirit of the original building.
Long term
The project extended over eight years of studies and works.
It was marked by numerous external events (COVID, the war in Ukraine), unforeseen circumstances (groundwater level, air pollution, old foundations) and changes in direction (geothermal energy was studied and ultimately abandoned for scheduling reasons).
It also benefited from new working methods (3D scanning, remote collaborative working, digital models).
The works were divided into around ten packages, themselves divided into subpackages, to shorten the construction period. In return, their coordination and the boundaries of responsibility between contractors had to be carefully managed.
Stable multidisciplinary team
Among the many parties involved who succeeded one another from 2018 onwards, the stability of the bureau greisch team was a considerable asset.
Two engineers, one responsible for the structural engineering studies and the other for building services and energy, coordinated the project from the start of the studies through to the completion of the works. They were supported by a large team of colleagues specialising in concrete and steel structures, heritage, building services, lighting, energy, civil engineering structures and infrastructure. Together, they delivered the amount of work that one person would accomplish over an entire career.
Project team
- Client: Fondation KANAL
- Architect: Atelier Kanal architects (NoA Architecten – EM2N – Sergison Bates Architecten)
- Engineering consultants
- Structural engineering and building services: Buro Happold / Bureau greisch
- Acoustics: Khale Acoustics
- Façades: Gevelinzicht
- Quantity surveyor: ELD
- Health and safety consultant: Ervico
- Energy performance of buildings (EPB): Egeon
- Fire engineering studies: FESG
- Contractor: BPC- Blaton