The Pisselet flood storage area was officially opened on Monday 23 November. The scheme’s main purpose is to protect a village near Grez-Doiceau from flooding when the Pisselet stream overtops its banks. Managing surface water runoff has become crucial in the current climate.
In 2020, bureau greisch carried out a feasibility study that included a mapping analysis and hydrological modelling by ULiège. Bureau greisch regularly draws on this expertise for other projects, including those on the Grande Gette and the Houssière. The feasibility study identified the most suitable site for the flood storage area, and the preliminary design confirmed the choice. At that stage, bureau greisch also sized the main structures, including the embankment. Designed in compacted lime-treated soil, the embankment took into account stability, permeability, crest height and the extent of inundation. The hydrological study provided the basis for estimating the temporary storage capacity and determining the return period of the rainfall events the scheme can accommodate. A calibrated sluice gate in a reinforced concrete structure cast in situ controls the outflow. During extreme rainfall events, an emergency spillway allows water to discharge once the flood storage area reaches its maximum water level.
Landscape integration – balancing flood protection and care for the environment
Because the scheme is located on private property, the embankment had to blend into the surrounding landscape. Bureau greisch designed it with gentle slopes and a curved alignment, working with Canevas, the architectural practice responsible for landscape integration and the 3D visualisations.
The earthworks were carried out in stages to minimise disruption to the property and retain as many trees as possible. Particular care was taken to protect the root systems of larger trees. New planting downstream was planned as compensation.
Project team
- Client: Province Brabant Wallon
- Client’s representative during construction: inBW
- Architect: Bureau Canevas
- Civil engineering consultant: bureau greisch
- Hydrological modelling: ULiège
- Contractor: Eecocure