Liege-Airport – TNT extension
Liege-Airport – TNT extension

    Liege-Airport – TNT extension

    Phase 1

    Expansion of the existing building by a construction with a length of 213 m and a width of 93 m.
    This new hub is separated from the old one by an Rf wall. The structure is entirely metallic. The height of the hall has been aligned with the existing building and allows for two floor levels between the floor slab and the roof.
    In a first step, a part of the 2nd intermediate level is realized on a surface of 4 000 m². This floor is suspended from the main beams of the roof structure.
    6,000 m² of the building is built in concrete to house part of the workshops and technical premises.
    The building was to be operational in 12 months.

    Phase 2

    Development of a complete intermediate level of 15,000 m² between the ground and the 2nd level.
    The floors were to be operational 6 months after the start of the studies.

    Phase 3

    Expansion of the existing building by a 46 m x 16 m construction and creation of 15 docks adapted to the unloading of vans.
    The building was to be operational 8 months after the beginning of the studies.

    Mission

    Phase 1 : Complete mission of stability, architecture and special techniques
    Phase 2 : Complete mission of stability
    Phase 3 : Complète mission of stability and architecture