work owner
Compagnie Eiffage du Viaduc de Millau.

architect
Sir Norman Foster

realization
from 2001 to 2004.

works costs
350 000 000 euros excl. vat.

location
highway A 75, upon the river Tarn. Near Millau, Aveyron (F).
> Google Maps

award
Fib award for outstanding structure 2006.


mission
Competition : complete study of the launched steel solution (winning solution).
Production studies : global and wind calculations, calculation per launching fase, dimensioning and calculation of the deck, the pylons and the staycables, dimensioning of the equipments, conception of the construction methods and the temporary works, assistance for the operations of launching, assembling and placing of the stays.

activity fields
> viaducts


introduction activities projects news contact job

Great viaduct of Millau

Multi cable stayed viaduct with 8 spans for a total length of 2 460 m located in a site where the geographical and climatic conditions are extremely severe : deep valley, heavy winds with high speeds and turbulency.
The superstructure is entirely of steel : the deck with an orthotropic plate (28 m width, 4,20 m high) and the 7 pylons (90 m high). Total steel weight : 50 000 ton.
The construction was made by launching from both valleysides and is a triple world record : launching of 171 m long spans, up to 280 m high (junction above the river Tarn) and a total weight of 20 000 ton for the last launching. The highest temporary support was 175 m.

Great viaduct of Millau  Print version
Calculus model Calculus model
Contribution of Greisch office (7'30) Contribution of Greisch office (7'30)
Flash animation Flash animation
Launching system Launching system
Photos of the building site Photos of the building site
Photos of the finished project Photos of the finished project