Logo bureau Greisch
 
 

work owner
SOFICO.
Public service of Wallonia, direction of waterways of Liège (SPW - DGO2 - DVHL)

works costs
civil engineering works and surroundings : 65 000 000 euros excl. vat

location
between the Albert canal and the Juliana canal, Lanaye (BE)
> Google Maps

Consortium company
Greisch/Coppée-Courtoy


mission
civil engineering studies (Greisch) and electromechanical equipment studies (Coppée-Courtoy)

activity fields
> civil engineering


introduction activities projects news contact job

Fourth lock at Lanaye

Construction of a lock (225 m - 25 m) with its ancillary structures and a pumping station/hydroelectric power plant, to the east of the existing complex of locks at Lanaye.
Tourist development of the site through its environmental management and the construction of service infrastructures for the benefit of the public. Studies in association with a landscape architect, a sculptor, a painter, a botanist, a conservation specialist.

Fourth lock at Lanaye  Print version