Logo bureau Greisch
 
 

work owner
Helio Charleroi

realization
from 2006 to 2007.

works costs
- total  investment: 100 000 000 euros excl. vat.
- buildings: 16 250 000 euros including 8 900 000 euros for stability

location
avenue du Spirou in Fleurus (BE)

mission
easibility study, basic design and execution project and assistance in the supervision of the work

activity fields
> stability


introduction activities projects news contact job

Heliographic printing works Helio

Complex of industrial buildings (25,000 m²) to house two wide rotary presses (4.32 m) and their accessory equipment. It includes eight halls with a height of 7 to 16 m, a building made entirely of concrete and a 70 m technical walkway.
The shell of the buildings and the floor slabs which are designed to withstand loads of 50 to 100 kN/m² are founded on piles (1,100 piles of 800 to 1,750 kN with a total length of 12,700 m).
The structure of the halls is comprised of prefabricated concrete columns and beams while all the bracing is made of steel. The raft foundations and pits were made with 10,000 m³ of concrete cast on site.
The main difficulty of the project was the rhythm of work which meant that the studies had to be completed in real time, that is, the «process» information was sent during the construction work.