work owner
conseil régional de la Réunion

architect
A Spielman

realization
from 2006 to 2009.

works costs
45 000 000 euros excl. vat

location
route des Tamarins, Trois-Bassins, Réunion island (FR)
> Google Maps

mission
execution study (civil engineering and steel structure)

activity fields
> bridges


introduction activities projects news contact job

Bridge of Grande Ravine - on the island Réunion

This bridge is part of the new road ‘route des Tamarins’, 2 x 2 lanes, that aims to reduce the traffic on the road along the west coast of the island.
This bridge 288 m long crosses a 160 m deep breach.
The deck made of orthotropic steel plates lies on two counters of prestressed concrete, inclined with 20°.
The counters are restraint in the abutments and their summits are holded by cables located in the deck.
They are constructed with the cantilever method. The abutments works as counterweights. The two halves of the deck are pushed from each bank and fi xed at the middle of the bridge.